Every new handset release triggers the same conversation: the model is announced, buyers want stock, and nobody is sure how long a new mould really takes. The honest answer is that the tooling itself is rarely the bottleneck. Approval loops are.
The figures below assume a factory that already runs this category, a customer who can supply a physical sample handset, and a straightforward single-colour case. Add time for anything decorative.
| Stage | Working days | Output you should receive |
|---|---|---|
| Sample handset or 3D data confirmed | 1 to 3 | Written confirmation of the reference model and variant, so nobody builds against the wrong one. |
| Structure design and draft analysis | 3 to 5 | 2D drawing with wall thickness, draft angles and the shut-off plan. This is the document to argue about now, not later. |
| Electrode and cavity machining | 7 to 12 | No output for you. Ask for photographs of the cavity block as a progress check. |
| First trial (T1) | 1 to 2 | Typically 3 to 8 pieces, unmounted, no surface texture. Judge fitment only, ignore cosmetics. |
| Correction round | 3 to 7 each | Revised samples. Budget for one or two rounds; more than three indicates the design was rushed. |
| Texture or surface treatment | 2 to 4 | Samples with the final finish. Colour and gloss can only be judged at this point. |
| Pilot run and sign-off | 3 to 5 | Small production batch, packaging trial, written approval of the golden sample. |
A clean programme therefore lands somewhere between 25 and 40 working days. A programme that hits a structural problem, such as a camera cut-out that interferes with the lens ring or a side button that does not return cleanly, more commonly runs 45 to 60.
In our experience the delay is almost never the machining centre. It is one of four things, in this order of frequency:
Mould quotes vary by a factor of three for the same model, which makes them hard to compare. Ask for the quote broken into these lines and the comparison becomes possible.
| Line item | What drives the number |
|---|---|
| Cavity machining | Number of cavities per mould. More cavities means a higher tooling cost and a lower unit price; it only pays back above a few thousand pieces per run. |
| Trial shots | Material consumed during T1, T2 and the pilot run. Often quoted separately, sometimes absorbed. |
| Texture | Chemical etching or sandblast. A fine matte finish costs less than a deep geometric texture that needs a second electrode. |
| Correction rounds | The contentious one. Establish in writing who pays for a correction caused by a design error versus one caused by your changed requirement. |
| Sampling and freight | Courier for each sample round. Small in money, large in schedule. |
Paying 100% of tooling up front removes every incentive to finish on time, and it leaves the question of who actually owns the tool unanswered. Ownership is a separate decision, covered in tooling ownership for OEM orders. A structure that works for both sides releases money against deliverables rather than dates:
When a launch date is fixed, the question becomes which stages can run in parallel. Three of them can, and they are the three most suppliers leave sequential out of habit.
What cannot be compressed is the correction loop. Skipping T1 and going straight to a textured sample is the single most common way a programme slips by a month, because a fitment problem discovered after texturing requires stripping the surface back off the steel.
Tooling a model before the retail handset exists is a gamble on dimensions that are still moving. The lower-risk route is to prove the process on the current generation, then cut steel within days of the new handset reaching your supplier. If a buyer needs stock on announcement day, the only realistic plan is to hold finished goods of the previous model and accept a short gap.